2020.05.14_Resident_Bedroom1.jpeg  2020.05.14_Resident_Bedroom2.jpeg

The millwork for the resident bedrooms was installed this week. Each individual bedroom room is equipped with a bed, wardrobe, desk, and chair.  

April 23, 2020

2020.04.23_Recreation_Project2.jpeg  2020.04.23_Recreation_Project.jpeg

Galusha & Sons started work on our new walking path today. Our youth are excited to have a place to take a leisurely stroll or ride their bikes on campus. 

April 10, 2020

2020.04.07_Gypsium_Board_1.jpeg  2020.04.07_Gypsium_Board_2.jpeg

The inside of the RTC project is really taking shape. Drywall installation is on-going and should be completed at the end of the month. 

March 20, 2020

Work continues on the RTC project during the COVID-19 crisis as it falls under an essential project in accordance with state guidelines. Our team is taking every precaution to comply with approved social distancing measures and enhanced cleaning and sanitation procedures, and we continue to take every possible step to ensure safety

March 20, 2020

2020.03.20_Siding3.jpeg    2020.03.20_Siding2.jpeg

The siding is just about completed on the RTC building. 

March 3, 2020

2020.03.03_Windows_1.jpeg   2020.03.03_Windows_2.jpeg

The installation of the windows in RTC project has begun. We hope to have all of the exterior windows in by the end of next week.  

February 5, 2020

 2020_02_05_Roof_1.jpeg  2020_02_05_Roof_2.jpeg

The installation of the roof began this week and should be completed by the end of the month. 

January 15, 2020

 

2020.01.15_Trusses_1.jpeg      2020.01.15_Trusses_2.jpeg

The truss installation has begun on the RTC project. We hope to be fully enclosed by the end of February. 

 

December 30, 2019

2019.12.30_Wood_panels_1.jpeg    2019.12.31_Wall_Panels.jpeg

We received the first of the wall panel delivery today and hope to see them standing by the end of the week. 

December 28, 2019 

    2019.12.28_Slab_1.jpeg 2019.12.28_Slab_3.jpeg

With the warmer temperatures, the slab of the RTC project was poured today. 

December 11, 2019

concrete_blnkt_12.11.19_37.JPG   concrete_blnkt_12.11.19_38.JPG

Our Campus Project Youth Ambassadors watched as our contractors prepped the site for the slab pour next week.