Skip to main content

March 20, 2019

pipes and rossetti tour 3.25.19  (8).JPG  pipes and rossetti tour 3.25.19  (6).JPG

Galusha & Sons will be onsite for the next 2 weeks to update our storm management system. While this work occurs, construction parking has been displaced to Academy Road. As always if you have questions or concerns, please email Northern Rivers' Project Manager at This email address is being protected from spambots. You need JavaScript enabled to view it.

 

March 11, 2019

 inside updates 3.11.19  (7).JPG   inside updates 3.11.19  (15).JPG

This week painters will be on-site to begin priming the walls of the Behavioral Health Care Center. 

February 26, 2019

The Residential Treatment Center project was presented to the City of Albany Planning Board, Tuesday, February 26.  We anticipate having approval  March 26th.

February 22, 2019

siding 2.21.19  (17).JPG   siding 2.21.19  (33).JPG

Exterior trim and siding work continues on the Behavioral Health Care Center. 

February 8, 2019

Ambassadors 02.04.2019  (29).JPG   sheet rock 02.11.19  (6).JPG

Door frames and drywall installation continues in the Behavioral Health Care Center. Electrical circuits for rooms and lighting have been installed. Exterior Trim and Siding work will begin next week. 

January 29, 2019

inside pics 1.29.19  (4).JPG  inside pics 1.29.19  (9).JPG

Installation of PVC window trim and molding continues. With the completion of the window trim, the siding and brickwork can begin. Plywood backing is currently being installed. The sheetrock and ceilings will be added in the next few weeks.

January 24, 2018

Northern Rivers is excited to announce a new development to our campus construction. As the next step in the process, and as dictated by new regulations in the City of Albany, we will host a public meeting to present our district plan to nearby property owners, Monday, January 28, 2019, at 5:30 p.m. at the Sidney Albert Training Institute (SATRI), 60 Academy Road, Albany, NY 12208. This brief informational session will be conducted by the consulting engineers and land surveyors with the general contractor and project architect, as well as agency leadership. They will provide details on the construction process and answer any questions you may have.  We hope you will join us for this meeting!

January 14, 2019

  hill pics 1.14.19  (52).JPG  3FA6DB92-1182-4406-9218-6DADBCE62DA8.jpg

The residential area roof in the Behavioral Health Care Center is almost complete. The Roof Top Air Handling Unit (RTU) and other roof equipment will installed next week. 

January 7, 2019

ambassadors 1.7.19  (39).JPG  hill pics 1.14.19  (26).JPG

Youth Ambassadors toured the Behavioral Health Care Center and marveled at the progress. 

January 3, 2019

biz dev tour 1.3.19  (4).JPG  biz dev tour 1.3.19  (17).JPG  

The installation of roof trusses and sheathing has begun in the residential area of the building. 

December 28, 2018

shingles and trusses 12.27.18  (3).JPG  shingles and trusses 12.27.18  (6).JPG

Window installation began this week. The clinical area of the building should be weather tight in the next few weeks.