Skip to main content

December 20, 2018

roof progress 12.20.18  (5).JPG   roof progress 12.20.18  (54).JPG

Star Roofing is on site preparing to shingle the roof, and Tech Valley has been actively installing the interior wall tracks. 

December 11, 2018

roof progress 12.11 (3).JPG  roof progress 12.11 (8).JPG 

The roof trusses and sheathing are almost complete in the clinical area. Shingle installation will begin next week. 

December 5, 2018

Sheathing 12.05.18.jpg  roof beginning 12.04.18  (28).JPG

Tech Valley has begun installing the exterior sheathing of the clinical wing. 

November 26, 2018

IMG_0436.JPG  IMG_0443.JPG

Dorsey Construction & General Construction has begun installing the trusses for the clinical portion of the building. 

November 8, 2018

IMG_8724.JPG    IMG_8730.JPG

 

October 26, 2018

slab and frame 10.26.18  (26).JPG  slab and frame 10.26.18  (38).JPG

Ragone Foundations began pouring the concrete slab. The slab will be complete early next week. Once the slab in place, BBL and subcontractors will begin to enclose the building. 

October 12, 2018

003.JPG     018.JPG

We're going vertical! 

October 3, 2018

2018.10.03 underground utilities(2).jpg   2018.10.03 underground utilities.jpg

Platt Plumbing has been onsite the last few weeks installing the underground sanitary, grease and storm lines. 

September 26, 2018

2018.09.26 Youth Ambassadors (1).JPG   2018.09.26 Youth Ambassadors (6).JPG

The Campus Project Youth Ambassadors met with BBL's site supervisor to learn about the project progression. 

September 13, 2018

IMG_0317.JPG  IMG_0318.JPG

Ragone Foundation is preparing for their last big concrete pour. They will have 6-7 concrete trucks on site today to pour the remaining walls of the residential wings. 

August 31, 2018

more concrete 8.28.18  (12).JPG  ProCore (4).JPG

Ragone Foundation has been pouring footings for the exterior walls of the buidling, and everyday we see more of the footprint of the new building.