December 20, 2018
Star Roofing is on site preparing to shingle the roof, and Tech Valley has been actively installing the interior wall tracks.
December 20, 2018
Star Roofing is on site preparing to shingle the roof, and Tech Valley has been actively installing the interior wall tracks.
December 11, 2018
The roof trusses and sheathing are almost complete in the clinical area. Shingle installation will begin next week.
December 5, 2018
Tech Valley has begun installing the exterior sheathing of the clinical wing.
November 26, 2018
Dorsey Construction & General Construction has begun installing the trusses for the clinical portion of the building.
November 8, 2018
October 26, 2018
Ragone Foundations began pouring the concrete slab. The slab will be complete early next week. Once the slab in place, BBL and subcontractors will begin to enclose the building.
October 12, 2018
We're going vertical!
October 3, 2018
Platt Plumbing has been onsite the last few weeks installing the underground sanitary, grease and storm lines.
September 26, 2018
The Campus Project Youth Ambassadors met with BBL's site supervisor to learn about the project progression.
September 13, 2018
Ragone Foundation is preparing for their last big concrete pour. They will have 6-7 concrete trucks on site today to pour the remaining walls of the residential wings.
August 31, 2018
Ragone Foundation has been pouring footings for the exterior walls of the buidling, and everyday we see more of the footprint of the new building.